Tápiószentmárton

Turnkey delivery of the municipal wastewater treatment plant in Tápiószentmárton: cyclic technology with sludge dewatering, with a treatment capacity of 1,800 m3/day.

Tápiószentmárton

Project overview

Treatment capacity

1 800

m3/day

Population equivalent

~17 000

PE

Our role

As main contractor, we prepared the permit and detailed designs, delivered the entire plant on a turnkey basis and managed the trial operation.

01

The client

The client was the Municipality of Tápiószentmárton. The plant is operated by TRV Zrt..

02

What we did

The plant's technology: cyclic technology with sludge dewatering. It has a hydraulic capacity of 1,800 m3/day and a biological capacity of ~17,000 PE. We also carried out servicing and maintenance at the plant.