Tápiószentmárton
Turnkey delivery of the municipal wastewater treatment plant in Tápiószentmárton: cyclic technology with sludge dewatering, with a treatment capacity of 1,800 m3/day.

Project overview
Treatment capacity
1 800
m3/day
Population equivalent
~17 000
PE
Our role
As main contractor, we prepared the permit and detailed designs, delivered the entire plant on a turnkey basis and managed the trial operation.
01
The client
The client was the Municipality of Tápiószentmárton. The plant is operated by TRV Zrt..
02
What we did
The plant's technology: cyclic technology with sludge dewatering. It has a hydraulic capacity of 1,800 m3/day and a biological capacity of ~17,000 PE. We also carried out servicing and maintenance at the plant.