Szeremle
Construction of the Szeremle agglomeration municipal wastewater treatment plant with biological lines, a sludge line and sludge storage, with a treatment capacity of 311 m3/day.

Project overview
Treatment capacity
311
m3/day
Population equivalent
3 127
PE
Our role
As general contractor, besides the complete construction we obtained the necessary permits, prepared the detailed and as-built designs and ran the trial operation.
01
The client
The client was the Municipalities of Szeremle and Bátmonostor. The plant is operated by Bajavíz Kft..
02
What we did
The plant was built with biological lines, a sludge line and sludge storage. Alongside the complete construction works, we also handled permitting, the detailed and as-built designs and the trial operation.