Szécsény
Turnkey delivery of the municipal wastewater treatment plant in Szécsény: cyclic technology with sludge dewatering, with a treatment capacity of 2,300 m3/day.
Project overview
Treatment capacity
2 300
m3/day
Population equivalent
~24 000
PE
Our role
As main contractor, we prepared the permit and detailed designs, delivered the entire plant on a turnkey basis and managed the trial operation.
01
The client
The client was the Municipality of Szécsény. The plant is operated by ÉRV Zrt..
02
What we did
The plant's technology: cyclic technology with sludge dewatering. It has a hydraulic capacity of 2,300 m3/day and a biological capacity of ~24,000 PE. We also carried out servicing and maintenance at the plant.