Turnkey delivery of the municipal wastewater treatment plant in Sándorfalva: cyclic technology with sludge dewatering, with a treatment capacity of 2,250 m3/day.

Project overview
Treatment capacity
2 250
m3/day
Population equivalent
~12 550
PE
Our role
As main contractor, we prepared the permit and detailed designs, delivered the entire plant on a turnkey basis and managed the trial operation.
01
The client
The client was the Municipality of Sándorfalva. The plant is operated by Alföldvíz Zrt..
02
What we did
The plant's technology: cyclic technology with sludge dewatering. It has a hydraulic capacity of 2,250 m3/day and a biological capacity of ~12,550 PE. We also carried out servicing and maintenance at the plant.