Komárom
Expansion of the municipal wastewater treatment plant in Komárom with two biological lines, a sludge line and a new 400 m3/h tertiary membrane post-treatment stage.

Project overview
Treatment capacity
8 000
m3/day
Population equivalent
58 000
PE
Suspended solids removal efficiency
>98,7
%
Our role
As general contractor, we carried out the permit and detailed design and the construction, mechanical and electrical works within the site, supplied and installed the equipment and ran the trial operation of the expanded plant.
01
The client
The client was the Municipality of Komárom. The plant is operated by ÉDV Zrt..
02
What we did
The expansion comprised two new biological lines, a sludge line and a 400 m3/h tertiary membrane post-treatment stage. We delivered all works within the site (as a “small general contractor”), from design to trial operation. We also carry out servicing and maintenance at the plant.
Outcome
The expanded plant operates at 8,000 m3/day, with a suspended solids removal efficiency above 98.7%.