Csákvár

Expansion of the municipal wastewater treatment plant in Csákvár with two new continuous-process biological lines and a sludge line, to a treatment capacity of 750 m3/day.

Csákvár

Project overview

Treatment capacity

750

m3/day

Population equivalent

5 563

PE

Our role

As general contractor, we carried out the detailed design and the construction, mechanical and electrical works within the site, supplied and installed the equipment and ran the trial operation.

01

The client

The client was the Municipality of Csákvár. The plant is operated by Fejérvíz Zrt..

02

What we did

We delivered all works within the site (as a “small general contractor”): detailed design, construction, mechanical and electrical works, supply and installation of the equipment, and the trial operation of the expanded plant. We also carried out servicing and maintenance at the plant.