Nestlé Hungária Co. Ltd. The pre-treatment plant is ready.
The pre-treatment unit designed to treat the 625 m3/d flow of the pet-food processing plant has been completed. The preparation and submission of the authorization plans, preparation of detailed design, delivery and installation of all equipment and all site-construction works were all done in a record time of only one and a half months. The equipment is already running treating wastewater, while Inwatech is performing the start-up works. The one-week-long performance test will begin on 8th June, 2011. after the commissioning works.